The first architect I worked for never understood how other architects could refuse to look at new products and new processes for construction. In 30+ years of practice, she always felt there was something new to learn. Architecture is an evolving profession, and why limit oneself to the way work has been done for the last 100 years?
To that end, I’ve just gone through one of those learning experiences and am still processing what to take away.
A contractor contacted me recently to assist with assembling a bid for one of his past clients. While I am quite accustomed to working on bidding from the client/architect side, being the one responsible for finding subcontractors, answering questions, interpreting drawings, etc. really gave me a new perspective.
First and foremost, I had to separate myself as an architect from what I was seeing as I reviewed the drawing set. Flipping through the pages and saying “I wouldn’t have drawn it that way” wasn’t going to get me where I needed to go. However, having an architect’s eye allowed me to ask some questions to help clarify issues before the subs came to me asking what to do and how to bid.
Second, I have a new appreciation for finding the right subcontractors, especially when you’re looking at an aspect you’re not familiar with. In this instance, locating the right company to handle soil retention as the excavator dug down right along the property line was a challenge. Luckily, I was able to get some referrals and then track them down via Google. Which makes me wonder how anyone did this in the “old days.”
Not to mention the frustration of tracking down a particular product from a particular vendor – even with the manufacturer directing you who to call. I have yet to figure out if the companies I contacted are really busy, or if they’re not interested in providing the one door the project needed. Either way, three weeks after finally reaching someone, I still don’t have a number.
Which brings me to the last thing I learned about – allowances. I’m gaining a new appreciation for the word “allowance.” And for contractor’s having to place those in their bids. In the past, I’ve looked at allowances and wondered why that hadn’t been worked out already. The contractor has had plenty of time. The drawings were pretty straightforward. What’s the issue?
However, as I worked through this project, I have been required to list what should be firm bids as allowances. For example, the steel supplier/fabricator provided his best guess as of that day. With new tariffs going into effect, he could not guarantee that steel costs wouldn’t increase, especially by the time he began his work. And I experienced the same with the concrete sub. Dallas is a busy market, and we’ve seen concrete in the past jump 30% within one year.
We’re still rounding up a few estimates, so we can present what is essentially the best guess to the client. So my experience isn’t complete.
But I can recall telling interns that what I was asking them to do was a “learning experience.” Which they often took as code for “you’re going to hate doing this.”
However, after 20 years of practice, I’m having a learning experience. And finding out that’s not such a bad thing.
Feature photo by Tim Mossholder.